VillageReach has received significant funding as a result of GiveWell's recommendation (see details for 2010 and 2009). This page gives periodic updates on VillageReach's expansion in Mozambique, which we believe has been substantially aided by funding resulting from our recommendation.
Note: In addition to GiveWell's update of VillageReach progress in Mozambique, John Beale, VillageReach's Director, Strategic Development & Group Lead, Social Business Group has authored a post on our blog providing additional context about VillageReach's program and mission. For more, see John Beale's post.
Discouraging results from the first year of operation in two Mozambique project provinces have resulted in significant changes to VillageReach's plans for the project. VillageReach's transparency and commitment to collecting meaningful data remain outstanding, and are key to these issues' coming to light. See this guest blog from VillageReach on its explanation of the program and its mission. Below we provide more details on:
VillageReach has continued to provide meaningful analysis of its progress for public consumption. While many of the observations below suggest results are discouraging, we always prefer discouraging results to no reported results.
VillageReach reports:1
In both provinces, vaccine distributions and data collection did not occur in a number of months: "Distributions were completed in 11 of 16 months (69%) in Cabo Delgado and in 11 of 14 months (79%) in Niassa."2
Cabo Delgado: VillageReach attributes problems in Cabo Delgado to interruptions in funding for government staff per diems and fuel; in the original project plan, these items were to be funded from government budgets that were supported by an outside funder.3 As a result, VillageReach has decided, going forward, to provide funding for staff per diems when government funding is not available (per diems are 61% of the operational costs).4 VillageReach reports that in the four months following this change, distributions occurred to all health centers on time.5
Niassa: VillageReach has identified two major problems in Niassa: (1) the existing quality of the system and (2) funding constraints.
Staff have failed to consistently collect and enter monitoring data.6 As a result, VillageReach has conducted additional staff training and hired additional managers.7
As in Cabo Delgado, there have been interruptions in funding provided by the government for per diems and fuel. In addition, the project continues to be limited to 6 out of 16 districts due to lack of government funding. Going forward, VillageReach has agreed to fill funding gaps for per diems, but has not agreed to provide funding for fuel.8
The start date for work in Maputo province and Gaza was later than expected, and as a result baseline reports have been delayed. VillageReach has started work in only part of each province.
Maputo province: In March 2011, VillageReach reported that it expected to begin distributions in Maputo in mid-2011. Distributions began in part of the province in December 2011.9 A health center baseline survey from the province was previously expected in or shortly after October 2011, and a progress report in or shortly after January 2012.10 These reports are now expected in April and August 2012, respectively.11
Gaza: In August 2011, VillageReach reported that it expected to begin distributions in Gaza in September 2011. Distributions began in part of the province in November 2011.12 A health center baseline survey and a cost survey from the province were previously expected in or shortly after September 2011, and a progress report in or shortly after April 2012.13 These reports are now expected in March/April and July 2012, respectively.14
VillageReach is now planning to work in 4 rather than 8 provinces in Mozambique. While each provincial administration is different, a prevailing risk for the project continues to be securing adequate levels of government financial support and other forms of support. VillageReach has noted this risk from the beginning.
Two factors have lead to a change in our estimate for the cost-effectiveness of the project: (a) changes in VillageReach's expected costs and (b) changes in the number of additional children VillageReach expects to vaccinate.
VillageReach notes that some of the increase in budgeted costs is due to unexpected inflation in Mozambique and an increase in the value of the Mozambican currency relative to the U.S. dollar.17
In sum, the budget changes reduce expected costs of the project by $557,000.21 Note that the revised budget is one year shorter than the earlier budget. The implications of this change for VillageReach's room for more funding are discussed below.
As discussed above, VillageReach's cost estimates for the 4 provinces it is working in have increased and it is currently unsure whether it will expand to the remaining 4 provinces in the original plan. The facts that (a) VillageReach's overall budget has stayed roughly the same as it was; (b) it now intends to cover half as many provinces as it previously did; and (c) the four provinces it no longer intends to enter in the near term are the ones that had significantly lower baseline vaccination rates than the provinces it has already entered22 leads us to the conclusion that VillageReach's cost-per-child-vaccinated has increased. We have yet to fully nail down the details of this change, but we will post an update when we do.
VillageReach shared FY 2011 and first quarter FY 2012 revenue data with us,23 as well as revenue projections for the remainder of FY2012 as of December 31, 2011.24
Our current room for more funding estimates are based on annual expected revenue of $980,000 in FY201225 and $850,000 in FY2013 and FY2014 (excluding contracts).26 These are estimates VillageReach has provided. VillageReach told us that only revenues that it believes with high confidence it will receive are included in "anticipated" revenue for FY2012.27 The revenue projections for FY2013 and FY2014 are based on rough estimates of individual and foundation giving.28
VillageReach's expected total costs for the project have been reduced slightly, but the number of provinces has been been cut in half and as a result VillageReach is now only budgeting through FY2014 instead of FY2015. Since VillageReach has reduced the budgeted timeframe for the project by a year, expected revenues for the project have been reduced by $850,000.29
VillageReach received $130,000 in GiveWell-influenced donations in the first quarter of FY 2012 (October to December 2011).30
We estimate that VillageReach has a funding gap of $1.44 million for its work in its first four provinces.31 This does not include room for more funding in the other four provinces where it has put further work on hold.32 Without further budget changes or additional revenues from sources that are not currently anticipated by VillageReach, we estimate that project will be out of money by mid-2013.33
Through following VillageReach's current scale-up project in Mozambique, we have learned more about the challenges to high quality data collection in the country, and have sought to improve our understanding of the quality of the pilot project evaluation. In a separate report on the evaluation of the Cabo Delgado pilot project, we examine two pieces of evidence from the pilot project evaluation: changes in vaccine stockouts in clinics served by VillageReach and province-level changes in vaccination rates in Cabo Delgado and neighboring provinces.
In our review of VillageReach, we focus primarily on its Mozambique program because we believe individuals' donations primarily support this program.34 VillageReach also implements programs in other countries as projects that are contracted with specific funders.
Our previous understanding of these projects was that spending on a project followed the signing of a contract in which a funder agreed to pay all costs of the project. VillageReach has told us that past contract engagements have been fully paid for by funding restricted for these engagements.35
After further discussion with VillageReach, it is now our understanding that the timeline for contract engagements is often not as straightforward as we had assumed. VillageReach staff, primarily those based in the US, may work on a variety of projects and programs, including the Mozambique program. VillageReach’s forecast of expenditure and related revenues (from foundations, individuals and contract sources) is based on its visibility into pending opportunities. The organization may have excess capacity of staff from time to time, as it gains and completes its work. As a result, unrestricted funds may need to be used to cover this excess capacity until new programs or contracts begin.36 Therefore, it is not clear that contract revenues and spending will always match. If VillageReach fails to win enough contract funding to cover its contract engagement budget, the effective cost of the Mozambique project may rise because unrestricted funds may be reallocated to cover the contract budget. VillageReach told us that it will reduce its contract budget if revenues are lower than expected, in order to limit using unrestricted funding.37 As of February 2012, VillageReach projected a $215,000 funding gap for contracts and a $125,000 funding gap for restricted foundation grants (these grants may be restricted to either Mozambique or non-Mozambique projects).38 VillageReach appears to have surplus from FY2011 for non-Mozambique projects.39
In our March 2011 update on VillageReach, we wrote:
We misinterpreted the study. The sample for the study was 12 to 23 month olds; under 12 month olds were not surveyed.40 The vaccination rate for "children below 12 months of age" referred to the percentage of children who were vaccinated before they turned a year old, not the percentage of current children under the age of 12 months who were vaccinated (since this group was not included in the sample).
Furthermore, because the study was carried out in April 2010, none of the children would have been vaccinated during VillageReach's pilot project.41
Therefore, our previous statement was incorrect.
We noted previously that there was a global shortage of the pentavalent vaccine, due to the World Health Organization decertifying a supplier. In August 2011, a second supplier was decertified.42 In January 2012, VillageReach told us that the global supply problems had been resolved, but that there had been difficulties in shipping vaccines within Mozambique (from the central level to the provincial level) due to insufficient space on domestic airlines.43
No additional progress reports were expected since the last update. VillageReach told us that it is collecting monthly data in the province but that it is only able to share progress reports with us every 6 months, due to government restrictions on data sharing.45 We expect the next progress report from Cabo Delgado in, or soon after, August 2011.46
VillageReach told us that the issue discussed in the previous update regarding delays in the flow of funds to the provincial government has been resolved and distributions are going ahead as planned. It told us that the delays were caused by the flow of funding to the government.47 VillageReach has not received reimbursement for the funds it had lent the government, but told us that it still expects to.48
The vaccination coverage baseline survey in Niassa covered 6 districts selected by the government "to represent 3 well-performing and 3 poorly-performing districts"49 (and is representative within these districts).50 We are concerned that these districts may not be representative of the province as a whole, and that the future evaluation of VillageReach's impact in the province could be inaccurate as a result. VillageReach told us that it will compare the baseline results with 2011 Demographic and Health Survey (DHS) data (expected to be available in late 2012 or early 2013) as a check of their accuracy. It also told us, "We consulted with Mark Kane [an epidemiologist and vaccination expert who originally advised us on our initial program evaluation] who determined that it meets our provincial level baseline needs."51
Note on quality of the Niassa 6-month report
We agree with VillageReach that these progress reports may not, on their own, be the best way for VillageReach to communicate its progress to us, and VillageReach has offered to "provide a summary written view of our opinions on the progress and challenges" with each future progress report, though we do not yet know if VillageReach will clear these summaries for public posting because of issues related to its relationship with the Mozambique government and what information it can share publicly.
We expect the next progress report from Niassa in, or soon after, September 2011.63
The government of Mozambique conducted a survey of vaccination rates in the province of Maputo in 2009,64 which VillageReach plans to use, together with the 2011 Demographic and Health Survey results, as the baseline vaccination coverage survey for evaluating its work in the province.65
Based on the baseline study, current vaccination rates in Maputo seem extremely high66 - significantly above the levels VillageReach used when it estimated the impact of its program (VillageReach has not been granted permission by the government to share details publicly).67 Given the high starting rate of vaccination in the province, we expect the "cost per additional child vaccinated" in Maputo to be substantially higher than previously expected.
VillageReach told us that it chose to work in Maputo because the province expressed a desire to work with it and that it believes there is room for improvement in areas other than vaccination rates.68 We have not seen evidence that VillageReach has the ability to observe and estimate humanitarian effects of improvements other than increases in vaccination rates.
We expect a progress report from Maputo in, or soon after, January 2012.69
In our previous VillageReach update, we noted that there was a global shortage of the pentavalent vaccine, which may have partially caused stock outs of the vaccine in the provinces in which VillageReach is active. When we asked VillageReach whether this situation had changed, it told us that it had seen improved supplies in Niassa and Cabo Delgado.70 VillageReach told us that the government has not given it permission to share data on stock levels.71 We will expect to see this improvement reflected in future progress reports.
We estimate that, based on conservative revenue projections, VillageReach has a funding gap for its Mozambique project of about $965,000. We estimate that VillageReach has sufficient funding for the Mozambique program through 2013, but that, with current projections of future funding and costs, it would run out of money in mid-2014.72
In April 2011, we estimated VillageReach's funding gap at $1.03 million, but we later discovered errors in our calculation of secured and expected revenues (details in the footnote).73 We have tracked about $163,000 to VillageReach since mid-April (as of July 19, 2011); we underestimated VillageReach's funding gap by about $98,000 in April.
We have not requested an update on expected costs for the Mozambique project. Our current estimate of VillageReach's revenues is based (a) VillageReach's secured and anticipated funding for FY2011 as of March 31, 2011; (b) VillageReach's estimate of expected funding from individuals and foundations in future years (excluding funding resulting from a GiveWell recommendation); and (c) funds we tracked to VillageReach between April 1 and July 15, 2011.
Additional provinces:
In our review of VillageReach, we focus primarily on its Mozambique program because we believe individuals' donations primarily support this program.81 VillageReach also implements programs in other countries as projects that are contracted with specific funders. VillageReach told us that all current contract engagements are fully funded by restricted funding.82
In our main review of VillageReach, we discuss a project in South Africa that VillageReach expected to support, in part, with non-contract funding. VillageReach told us that this project has been cancelled.83
VillageReach also told us that it is no longer financially supporting the VidaGas project.84
We requested a full organization budget broken down by project as we have seen from VillageReach in the past, but it told us that it could not provide us with that breakdown because it had recently revised its budgeting system.85 Therefore, we have not been able to verify how unrestricted funding is spent.
In the course of discussing the problems with data collection in the first few months of the program in Niassa, some questions were raised about the quality of the data collected in VillageReach's pilot project. We have not yet explored these questions and plan to do so in the next few months. We will post updates on this page.
We have discussed the issue alluded to in this VillageReach blog post with VillageReach staff, and do not find it to be cause for concern.
VillageReach is active in Cabo Delgado, Niassa, and Maputo.86 Currently:
The overall expansion is substantially behind the schedule set out in July 2010 (on time in Cabo Delgado but six to twelve months behind for other provinces).87 Reasons for the delay are partly related to dialogue with the government but appear primarily due to insufficient funding (though revenue in 2010 closed VillageReach's entire "stretch funding gap" for the year, the vast majority of that revenue was not received or anticipated until December).88
VillageReach has provided new information on progress in Cabo Delgado, the first province where it has become active. (It also states that a baseline-coverage survey has been done in Niassa89 but is not yet public.)
Unfortunately, this supplier has not been successful in regaining that status. New suppliers have been pre-qualified by WHO this year but they require lead time to produce the volume necessary to match the demand. So, in short, Mozambique is not the only country affected but all GAVI countries are affected by this.
This issue may be partly responsible for the particularly high stock-out rates for this particular vaccine.95
Notes on the presentation and quality of the materials provided by VillageReach:
In discussions with VillageReach, we have learned more about the factors that go into expanding to a new province, aside from funding. In addition to funding its own operations and getting sign-off from the local health authorities, VillageReach must ensure that there is sufficient government funding earmarked for helping to carry out its program112 and that it has sufficient capacity of its own, which can involve a hiring process.113 VillageReach representatives have told us that these factors are relatively straightforward to address when funding on its own end is available, but these issues are worth keeping in mind as potential non-financial bottlenecks to expansion.
VillageReach, "Status of VillageReach Work Following 1-Year Evaluations (January 2012)," Pg 1.
VillageReach, "Health System Strengthening in Mozambique: Update (November 2011)," Pg 3.
"A very unfortunate consequence of the funding challenges and interruptions to distributions is an interruption to the data. The data collected as part of the DLS relies on visits to the health center, and without distributions there are no visits." VillageReach, "Status of VillageReach Work Following 1-Year Evaluations (January 2012)," Pg 3.
"The main finding of the Cabo Delgado evaluation was that there was a willingness and capacity to implement the DLS in the province, but they faced major funding problems in 2011 that led to the disruptions since June 2010...The arrangement in Cabo Delgado was that the DLS would be implemented with 3 partners: DPS provided funds management and implementation, funds from EGPAF [Elizabeth Glaser Pediatric AIDS Foundation], and technical assistance from VillageReach. However, the flow of funding from EGPAF to DPS was halted due to certain conditions in the sub-agreement between DPS and EGPAF." VillageReach, "Status of VillageReach Work Following 1-Year Evaluations (January 2012)," Pgs 1-2.
"We decided to allocate some backup funds for per diems in the province. These funds are to be used when EGPAF funds aren't available and are managed by VillageReach. This cost-sharing approach still demands that DPS fund the costs of fuel, which is 38% of the monthly operational cost. Monthly per diems cost $2,856 and fuel costs $1,800. DPS continues to pay the staff and indirect costs." VillageReach, "Status of VillageReach Work Following 1-Year Evaluations (January 2012)," Pg 2. 2856/(2856+1800) = 61.3%
"DPS Cabo Delgado happily accepted the cost-sharing approach and have been using VillageReach funds for the last four months of distributions, which happened to all health centers and on time." VillageReach, "Status of VillageReach Work Following 1-Year Evaluations (January 2012)," Pg 2.
"There continue to be challenges with collecting data and entering it in vrMIS. The result of these problems is continued limited analysis of the system in the province." VillageReach, "Status of VillageReach Work Following 1-Year Evaluations (January 2012)," Pg 3.
"To improve activities in the health centers, we worked with DPS to implement a pilot one-on-one health worker training in 2 districts...Verbal reports of the training indicate that it has been very successful, we plan to continue the training again later this month.
Another response to the quality problems in Niassa has been our hiring of additional support for the province." VillageReach, "Status of VillageReach Work Following 1-Year Evaluations (January 2012)," Pg 3.
"In 2011, there were interruptions to distributions in Niassa due to funding constraints...Throughout the year, the distributions have continued to be only to the health centers in 6 out of the 16 districts because of limited funding...
Our agreement is that if DPS doesn't have the funds to cover all districts and all health centers, they can ask VillageReach to pay for the per diems and they will pay for the fuel. This maintains their current financial commitment while expanding to all provinces. This arrangement started in December. The cost of this arrangement is $2,665/month for per diems paid by VillageReach and $2,415/month for fuel." VillageReach, "Status of VillageReach Work Following 1-Year Evaluations (January 2012)," Pgs 3-4.
"The distributions started in November for Gaza and December for Maputo. In both provinces the distributions went to only one zone..." VillageReach, "Status of VillageReach Work Following 1-Year Evaluations (January 2012)," Pg 4.
VillageReach, "Tentative Schedule for VillageReach Evaluation Activities (August 2011)."
VillageReach, "Tentative Schedule for VillageReach Evaluation Activities (January 2012)."
"The distributions started in November for Gaza and December for Maputo. In both provinces the distributions went to only one zone..." VillageReach, "Status of VillageReach Work Following 1-Year Evaluations (January 2012)," Pg 4.
VillageReach, "Tentative Schedule for VillageReach Evaluation Activities (August 2011)."
VillageReach, "Tentative Schedule for VillageReach Evaluation Activities (January 2012)."
See GiveWell, "Changes in VillageReach Budget (February 2012)."
VillageReach, "Mozambique Budget Change (February 2012)."
John Beale and Leah Barrett, phone conversation with GiveWell, January 12, 2012.
GiveWell, "Changes in VillageReach Budget (February 2012)."
VillageReach, "Health System Strengthening in Mozambique: Update (November 2011)," Pg 4.
See GiveWell, "Changes in VillageReach Budget (February 2012)."
GiveWell, "Changes in VillageReach Budget (February 2012)."
Mozambique National Institute of Statistics, "Multiple Indicator Cluster Survey (2008)."
VillageReach, "Budget Variance Report (FY2011)."
John Beale, email to GiveWell, February 10, 2012.
John Beale, email to GiveWell, February 10, 2012.
John Beale, email to GiveWell, March 4, 2011.
John Beale, phone conversation with GiveWell, February 16, 2012.
John Beale, email to GiveWell, March 4, 2011.
VillageReach, "Mozambique Budget with GiveWell Additions (November 2011, updated February 2012)."
Data from GiveWell's internal donation records.
VillageReach, "Mozambique Budget with GiveWell Additions (November 2011, updated February 2012)," Cell G24.
See GiveWell, "Changes in VillageReach Budget (February 2012)."
VillageReach, "Mozambique Budget with GiveWell Additions (November 2011, updated February 2012)," Cell E23.
"VillageReach has also contracted with other organizations to improve logistical systems in other countries, but generally hasn't used, and doesn't plan to use, funding from individuals for projects outside of Mozambique (with a few exceptions discussed below)." See our April 2011 review of VilllageReach.
VillageReach, "Contract Engagements (2011)."
John Beale, phone conversation with GiveWell, February 16, 2012.
John Beale, phone conversation with GiveWell, February 16, 2012.
John Beale, email to GiveWell, February 10, 2012.
VillageReach, "Mozambique Budget with GiveWell Additions (November 2011, updated February 2012)," Cell C34.
"The total sample size for the vaccine coverage survey was 211 children (planned 210 children) between the age of 12 months and 23 months." VillageReach, "Vaccination Coverage Baseline Survey for Cabo Delgado Province," Pg 11.
"In the 2010 survey only the 12-23 month age group was covered as they represent an age group that have been potentially vaccinated since the end of the first EPI programme supported by VillageReach with the DPS Cabo Delgado." VillageReach, "Vaccination Coverage Baseline Survey for Cabo Delgado Province," Pg 17.
World Health Organization, "Panacea Biotec DTP-Based Combination and Monovalent Hepatitis B Vaccines Delisted from WHO List of Prequalified Vaccines."
John Beale and Leah Barrett, phone conversation with GiveWell, January 12, 2012.
VillageReach, "Tentative Schedule for VillageReach Evaluation Activities."
John Beale and Leah Barrett, phone conversation with GiveWell, July 15, 2011.
VillageReach expects to conduct the evaluation in July and says that reports "would not be anticipated until at least one month following data collection activities."
VillageReach, "Tentative Schedule for VillageReach Evaluation Activities."
John Beale and Leah Barrett, phone conversation with GiveWell, May 12, 2011.
VillageReach, "Comments on GiveWell's VillageReach update (July 2011)," Pg 2.
"In the Cabo Delgado baseline, we selected the sample to represent the provincial level coverage rate. In the Niassa baseline, DPS wanted to get district-level (ie. sub-province) coverage rates but also had some restrictions in their own funding, limiting a larger study…We could only fit 6 districts in the budget. We consulted with Mark Kane (an epidemologist and vaccination expert who originally advised us on our initial program evaluation) who determined that it meets our provincial level baseline needs. DPS selected the 6 districts to represent 3 well-performing and 3 poorly-performing districts. The program is operating in 3 of the districts from the baseline and 3 districts not included in the baseline." John Beale, email to GiveWell, June 29, 2011.
"The survey was undertaken in six districts. In each of the districts a sample of ten hoursholds and ten villages that were selected on a random basis using probability proportional to size. The sample is representative of the districts covered under the survey." VillageReach, "Vaccine Coverage and Vaccine and Rapid Diasgnosis Tests Logistics Study: Niassa Baseline Survey (July 2010)."
John Beale, email to GiveWell, June 29, 2011.
VillageReach, "Comments on GiveWell's VillageReach update (July 2011)," Pg 2.
"In four of the six months studied, field coordinators left for the distributions without receiving per diems and were forced to use their own money to cover expenses. In January, the delay in the availability of funds was so great that no vaccines were distributed during the month." VillageReach, "Niassa Dedicated Logistics System Six-Month Process Evaluation (February 2011)," Pg 5.
John Beale, email to GiveWell, June 29, 2011.
VillageReach, "Comments on GiveWell's VillageReach update (July 2011)," Pg 2.
John Beale, email to GiveWell, July 29, 2011.
Examples of copied text:
Example 2:
John Beale, email to GiveWell, July 29, 2011.
John Beale and Leah Barrett, phone conversation with GiveWell, July 15, 2011.
VillageReach, "Comments on GiveWell's VillageReach update (July 2011)," Pg 3.
VillageReach expects to conduct the evaluation in August and says that reports "would not be anticipated until at least one month following data collection activities." VillageReach, "Tentative Schedule for VillageReach Evaluation Activities."
Dos Santos, et al. 2010.
John Beale and Leah Barrett, phone conversation with GiveWell, May 12, 2011.
Dos Santos, et al. 2010, Pg 13. (This document is in Portuguese. We used the Google translation service to examine it.)
In its plan for the project, VillageReach based its estimates of "incremental children vaccinated" on two assumptions: (1) "Children vaccinated with current system is based on estimates from coverage rate studies for Cabo Delgado and Niassa. All other provinces [including Maputo] based on national rate of 72%"; (2) "Total children forecasted to be vaccinated with new system is 80% in the first year, 85% in the second year, and 90% in the third year." VillageReach, "Health System Strengthening in Mozambique," Pg 7.
VillageReach believes there is room for improvement in Maputo in:
John Beale, email to GiveWell, July 29, 2011.
VillageReach expects to conduct the evaluation in December 2011 and says that reports "would not be anticipated until at least one month following data collection activities." VillageReach, "Tentative Schedule for VillageReach Evaluation Activities."
John Beale and Leah Barrett, phone conversation with GiveWell, July 15, 2011.
VillageReach, "Comments on GiveWell's VillageReach update (July 2011)," Pg 4.
VillageReach, "Comments on GiveWell's VillageReach update (July 2011)," Pg 4.
VillageReach, "VillageReach, "Mozambique Budget with GiveWell Additions (February 2011, updated July 2011)."
We assume this based on a scheduled 6-month progress evaluation scheduled for March 2012. VillageReach, "Tentative Schedule for VillageReach Evaluation Activities."
VillageReach, "Tentative Schedule for VillageReach Evaluation Activities."
VillageReach, "Comments on GiveWell's VillageReach update (July 2011)," Pg 5.
VillageReach, "Comments on GiveWell's VillageReach update (July 2011)," Pg 3.
John Beale, email to GiveWell, July 29, 2011.
John Beale and Leah Barrett, phone conversation with GiveWell, May 12, 2011.
John Beale and Leah Barrett, phone conversation with GiveWell, July 15, 2011.
"VillageReach has also contracted with other organizations to improve logistical systems in other countries, but generally hasn't used, and doesn't plan to use, funding from individuals for projects outside of Mozambique (with a few exceptions discussed below)." See our April 2011 review of VilllageReach.
VillageReach, "Contract Engagements (2011)."
John Beale and Leah Barrett, phone conversation with GiveWell, May 12, 2011.
John Beale and Leah Barrett, phone conversation with GiveWell, May 12, 2011.
"We don't have that breakdown currently, as we recently revised our budget formats." John Beale, email to GiveWell, June 29, 2011.
VillageReach, "'Room for More Funding' Analysis," Pg 1.
See VillageReach, "Mozambique Project Plan," which directly compares the previous and current schedules.
"VillageReach is active in Cabo Delgado, Niassa, and Maputo. The initial start last year in these provinces was slower than had been anticipated, primarily due to concerns about funding and some delays in dialogue with the government , but we now have good progress in all three provinces ... In the last six weeks of 2010 VillageReach received funding from individual donors well beyond expectations. Until this time it had not been clear what level of activity would be possible for the Mozambique program in 2011.
Because of this lack of visibility, we had not pursed any new DPS discussions late least year, except for Gaza, where [a funder] had already made it clear that they can provide funding for the Gaza provincial governments activities. Note that it can take some months of discussion with a provincial government before permission to work in the province is received and finances and personnel are allocated by the government." VillageReach, "'Room for More Funding' Analysis," Pg 1.
"Baseline assessments have been completed in both Cabo Delgado and Niassa and distributions are well underway." VillageReach, "'Room for More Funding' Analysis," Pg 1.
See chart in VillageReach, "Cabo Delgado Dedicated Logistics System Six-Month Process Evaluation (February 2011)," Pg 5.
See charts beginning at VillageReach, "Cabo Delgado Dedicated Logistics System Six-Month Process Evaluation (February 2011).," Pg 11. The chart on stock outs is particularly important to the question of whether VillageReach is succeeding in improving the efficiency of the local health system.
See our report on VillageReach.
"There has been a reduction in vaccine coverage from 2008 to 2010 (children below 12 months of age) of nearly 18 percentage points, although the vaccine coverage including children above 12 months of age is only slight lover than the 92.65 in 2008, 89% in 2010." VillageReach, "Vaccination Coverage Baseline Survey for Cabo Delgado Province," Pg 31.
"A key requirement of the Dedicated Logistics System is that the monthly funding mechanism to support the field coordinators and the distribution schedule are in place and operating without the need for external support. The distribution costs are covered by a partnership with [a funder], which results in full funding for the previously identified operational needs. However, discussions during the evaluation revealed that there are some challenges in the flow of funds from [a funder] to DPS related to the larger agreement between the partners (i.e. not limited to Dedicated Logistics System activities) that affected the availability of per diems for the November distribution. Additionally, in February the funds were not available for the distributions and DPS relied upon a loan from VillageReach to support the costs. Prior to this problem, the funding of the monthly distributions was working well. Without fixing the problem, there is a significant risk to the operations and outcomes of the Dedicated Logistics System." VillageReach, "Cabo Delgado Dedicated Logistics System Six-Month Process Evaluation (February 2011)," Pg 5.
VillageReach, "Cabo Delgado Dedicated Logistics System Six-Month Process Evaluation (February 2011)," Pg 11.
"Stock outs: Reports the number and percentage of health units having a stock level of 0 (termed a stock-out event) of any particular vaccine, EPI-related supplies, or rapid diagnostic tests. This indicator measures how well the logistics system is functioning to supply the health unit with vaccines and associated commodities to meet communities’ need for a full-month. The target for stock outs is 0% of the health units reporting, but 5% is an acceptable level. We expect stock outs to increase up to 40% at the start of the implementation of the dedicated logistics system as demand for vaccines increases (due to increased supply). After 6 months of implementation, we expect stock outs to decrease to 5% or below." VillageReach, "Cabo Delgado Dedicated Logistics System Six-Month Process Evaluation (February 2011)," Pg 21.
See chart at VillageReach, "Cabo Delgado Dedicated Logistics System Six-Month Process Evaluation (February 2011)," Pg 11.
VillageReach, "'Room for More Funding' Analysis," Pg 1.
"We had not pursed any new DPS discussions late least year, except for Gaza, where [a funder] had already made it clear that they can provide funding for the Gaza provincial governments activities. Note that it can take some months of discussion with a provincial government before permission to work in the province is received and finances and personnel are allocated by the government." VillageReach, "'Room for More Funding' Analysis," Pg 1.
"After Gaza, we will work on Inhambane next, with outreach to the government there expected once we have hired a new program manager; we have identified a strong candidate. We estimate the start of those discussions with Inhambane Province in early summer 2011." VillageReach, "'Room for More Funding' Analysis," Pg 2.
VillageReach, "'Room for More Funding' Analysis," Pg 2.
Costs for 2011-2012 including only the provinces of Cabo Delgado, Niassa, Maputo, Gaza, and Inhambane were a total of $1,771,717. "Mozambique Funding Gap" shows about $1,592,491 available, implying a remaining gap of $179,226. See VillageReach, "Mozambique Budget with GiveWell Additions," Cell H17 and VillageReach, "Mozambique Funding Gap."
VillageReach, "Revenue Attribution (2010)."
"We estimate approximately $850 in non-GiveWell unrestricted revenues/and or Moz-restricted revenues [ie. some foundations have this requirement, others do not] for this fiscal year, assuming $350-400k is from individuals and $450-500k comes from foundations." John Beale, email to GiveWell, March 4, 2011.
VillageReach states,
"You asked us for our thinking as to what funding amounts trigger what levels of activity …
- If VillageReach had raised $500,000 less in late 2010:
- VillageReach would still be active in Cabo Delgado, Niassa and Maputo.
- VillageReach would still be planning to pursue expansion in Gaza when the opportunity arises, probably a few months from now.
- VillageReach would not be planning on pursuing expansion beyond Gaza until/unless significant further funding came in.
- If VillageReach had raised $1,000,000 less in late 2010:
- VillageReach would still be active in Cabo Delgado, Niassa and Maputo.
- VillageReach would not be planning on any further expansion unless significant further funding came in and the program would have been at serious risk of ending prematurely."
This is consistent with our analysis of VillageReach's budget, which is similar to the analysis we show in "Mozambique Budget with GiveWell additions." VillageReach, "'Room for More Funding' Analysis," Pg 2.
VillageReach, "Revenue Attribution (2010)."
"Note we would also expect to start work in Manica Province before the end of FY2012. Sofala and Tete would follow at the beginning of FY2013 (ie., late CY2012/early 2013)." VillageReach, "'Room for More Funding' Analysis," Pg 2.
VillageReach, "Mozambique Budget with GiveWell Additions," Cell H18.
VillageReach, "Mozambique Budget with GiveWell Additions," Cell G22.
"If we raise up to $500k more than is forecast by the end of CY2011: VillageReach will likely still pursue the program as presented in the project plan, although there might be some modest acceleration.
If we raise $500k - $1M more than is forecast by the end of CY2011: VillageReach will likely accelerate planned discussions with the 7th and potentially 8th provinces.
If we raise any amount beyond $1M more than is forecast by the end of CY2011:
VillageReach may be able to accelerate discussions with the 8th province." VillageReach, "'Room for More Funding' Analysis," Pg 2.
In summary, VillageReach projects approximately $1 million in unrestricted, annual, non-GiveWell funding in the future. It requires $500,000 of this for general operations and $500,000 of this for its Mozambique project. Given this funding, VillageReach's Mozambique project would require a total of $1 million in addition to expected funding to fully fund the Mozambique expansion.
For example: "We had not pursed any new DPS discussions late least year, except for Gaza, where [a funder] had already made it clear that they can provide funding for the Gaza provincial governments activities. Note that it can take some months of discussion with a provincial government before permission to work in the province is received and finances and personnel are allocated by the government." VillageReach, "'Room for More Funding' Analysis," Pg 1.
"After Gaza, we will work on Inhambane next, with outreach to the government there expected once we have hired a new program manager; we have identified a strong candidate. We estimate the start of those discussions with Inhambane Province in early summer 2011." VillageReach, "'Room for More Funding' Analysis," Pg 2.